Todd Little , Landmark Graphics
ABSTRACT
One software product company found that its project duration estimation accuracy followed a lognormal distribution and the uncertainty range was nearly identical at all stages in the project life cycle. This conflicts with popular interpretation of the "cone of uncertainty" concept.
INDEX TERMS
software estimation, project management, uncertainty, risk management, process metrics
CITATION
Todd Little, "Schedule Estimation and Uncertainty Surrounding the Cone of Uncertainty", IEEE Software, vol. 23, no. , pp. 48-54, May/June 2006, doi:10.1109/MS.2006.82